Attaching the Solar Life to the mounting bracket

NOTICE

  • For easier installation of the power cable, a cable gland M25 (1.219.2501.50 + Locknut M25) can be used. These are sold separately.
  • Up to two data cables can be connected: one for the smart meter connection and one for the Ethernet connection.

To attach the Solar Life to the mounting bracket:

  1. Remove the trim cover and the sealing cover . See Removing and installing the covers.
  2. If the power and data cables need to enter through the back panel:
    1. Use a step drill and create the required 25 mm hole for the power cable entry and, if applicable, for the data cable entry .
    2. Install the M25 grommet in the power cable entry . Install the M25 Multi-hole grommet in the data cable entry .
    3. Route the power cable through the M25 grommet into the cable entry .
    4. If applicable, route the data cable(s) through the M25 Multi-hole grommet into the cable entry .
    5. NOTICE Make sure the M25 grommets are correctly seated in the cable entries. Do not connect the cables at this moment.

      

  3. Place the Solar Life onto the mounting bracket . Attach it with two T20 Torx bolts.
  1. If the power and data cables need to enter through the bottom cable entries:
    1. Route the power cable through the power cable gland .
    2. If applicable, route the data cable(s) through the data cable gland . If necessary, use a reducer to make sure the cable is sealed correctly.
    3. NOTICE Do not connect the cables at this moment.